Labour Cost Calculator
Estimate the total manpower cost of a job before you quote it: number of workers, duration in days, daily rate, and a contingency buffer for overruns.
How to estimate labour cost for a quote
Base Labour Cost = Workers × Days × Daily Rate. A 6-worker team at ₹550/day for a 20-day job costs ₹66,000 in wages. On top of that, experienced contractors add a contingency of 5–15% for rain days, rework and overtime — the difference between a profitable quote and an optimistic one.
The estimate is only half the job; the other half is knowing your actual cost as the project runs. Daily attendance against the estimate tells you by week two whether the job is tracking over or under — early enough to act, instead of discovering the overrun at final billing.
Frequently asked questions
How much contingency should I add to a labour estimate?+
Between 5% and 15% depending on the trade and season. Outdoor monsoon work and jobs with rework risk sit at the higher end; controlled indoor work at the lower end.
Should overtime be included in the estimate?+
If the deadline is tight, yes — estimate expected OT hours separately at your OT rate, or cover it inside the contingency buffer. Deadline-driven jobs routinely spend 5–10% of wage cost on OT.
How do I track actual labour cost against my estimate?+
Mark daily attendance per worker and record advances as they happen. The Laborbook app gives you actual man-days and wage liability at any point in the project, so you can compare against this estimate live.